When the Design menu > Steel Connections Design > Verify All Connections Passed command is used, the program reports if structural members passed the stress/capacity check.
Click the Analyze menu > Run Analysis command to run an analysis.
Click the Design menu > Steel Connections Design > Start Design/Check command to run a design.
Click the Design menu > Steel Connections Design > Verify All Connections Passed command.
ETABS will display a message indicating the outcome of the verification.
If the message indicates a connection(s) did not pass, repeat Step 3 until all connections pass.
Repeat Steps 1, 2 and 3 to verify the design and that all members pass.
If necessary, repeat Steps 4a and 4b until all members pass.