Form: Cable Material Property Overwrite
By default, the program uses the material properties associated with the section assigned to the cables. Use the Assign menu > Cable > Material Property Overwrites command to specify that a previously defined material property be assigned to a selected object(s).
Select the cable object for which the material property is to be overwritten.
Click the Assign menu > Cable > Material Property Overwrites command to access the Cable Material Property Overwrite form.
Use the Material Property Designated in the Cable Property Definition - This is the default option. When this option is selected, the material properties are those defined for the property assigned to the selected cable. This option can be used to reverse a material property overwrite.
Overwrite Material Property option and drop-down list - When this option is selected, choose the previously defined material property definition from the drop-down list. The chosen definition will be applied to the selected cable object.
See Also
Frame - Material Property Overwrites